During today’s Government meeting chaired by Prime Minister Bakytzhan Sagintayev, Minister of Energy Kanat Bozumbaev elaborated on the process of execution of the President's task to construct the Saryarka main gas pipeline along the route Kyzylorda-Zhezkazgan-Karaganda-Temirtau-Astana.

As part of the execution of the order of the Head of State, a videoconference meeting was held in the Ministry of Energy on March 7 with the participation of concerned government agencies, Akimats of Kyzylorda, Karaganda, Akmola regions and the city of Astana, and Samruk-Kazyna National Welfare Fund, during which the Roadmap for implementation of the Gas Infrastructure Project was approved and a working group was formed.

“We agreed to ensure the development and approval of design estimates and the allocation of land for the construction of the main gas pipeline along the route Kyzylorda - Zhezkazgan - Karaganda - Temirtau - Astana. Responsible executors: Ministry of Energy, Ministry of Investments and Development, Akimats of Kyzylorda, Karaganda and Akmola regions and KazTransGas. The deadline is July 2018,” – K. Bozumbaev said.

The Minister also noted that it is necessary to determine the scheme for financing the project by attracting funds from international financial institutions. The deadline is June 2018. Responsible for this are NMH Baiterek, Ministry of Finance, Ministry of National Economy, Ministry of Energy, NWF Samruk-Kazyna, NC KazMunayGas, KazTransGas JSC.

K. Bozumbayev stressed that the NWF Samruk-Kazyna needs to create or determine a subsidiary organization for the implementation of the project and to form the authorized capital at a sufficient level to attract financing. The deadline is June 2018. Those responsible: Ministry of National Economy, NWF Samruk-Kazyna, NC KazMunayGas, KazTransGas JSC.

“The launch of the construction of the main gas pipeline and the official ceremony of welding the first joint of the gas pipeline is planned for early July this year,” – K. Bozumbayev said.

Also, the Minister noted that in order to fill the main gas pipeline and ensure gas supply to consumers, Akimats of Karaganda, Akmola regions and Astana need to speed up the design and construction of gas distribution networks and synchronize the completion of the gas pipeline by July 2019.

Recall, on March 5, 2018, the Head of State in his Address to the People of Kazakhstan instructed to implement the construction of the Saryarka main gas pipeline along the route Kyzylorda - Zhezkazgan - Karaganda - Temirtau - Astana within a year or a year and a half.

www.primeminister.kz

Published: 13 March 2018