Saryarka gas pipeline to be completed Dec. 31, 2019 — Zhurebekov

Wednesday, 20 November 2019, 13:52:40

At a press conference in the government, Vice Minister of Energy Murat Zhurebekov spoke about the progress of the project of Saryarka gas pipeline construction along the Kyzylorda – Nur-Sultan route under the Five Social Initiatives of the First President – Elbasy Nursultan Nazarbayev.

One of the tasks set by the Head of State Kassym-Jomart Tokayev to the Ministry of Energy in the pre-election program is the timely completion of the first stage of the Saryarka gas pipeline with a view to supplying gas to the capital, northern and central regions of the country.

According to Zhurebekov, this section of the gas pipeline will allow delivering natural gas to the cities of Nur-Sultan, Karaganda, Temirtau, Zhezkazgan, as well as to residents of the settlements closest to the gas pipeline route.

To implement the project, the company AstanaGaz KMG was created. Its shareholders are Samruk-Kazyna Fund and Baiterek Holding.

The financing scheme and conditions were approved by the State Commission for the Modernization of the Economy in August 2018. So, 80.3 billion tenge is provided through the formation of the authorized capital of the project company AstanaGaz KMG JSC, 85 billion tenge is a bond loan of Unified National Pension Fund JSC and 102 billion tenge is a bond loan of the Eurasian Development Bank and Kazakhstan Development Bank JSC. The general contractor for the construction is KazStroyService.

Zhurebekov said that today the construction of the Saryarka gas pipeline to the city of Nur-Sultan is being completed.

It was noted that about 1,700 specialists and 1,000 units of special equipment were involved in the construction of the gas pipeline. To date, 1,061.3 km or 100% of the linear part of the pipeline has been welded and laid. At the same time, 963 km or 91% of the gas pipeline were tested.

In addition, work is underway on the construction of branch pipelines and five automated gas distribution stations, a gas metering station and a control point

In general, work is proceeding on schedule, and in December of this year, the construction of all facilities will be completed, including a gas pipeline, five units of automated gas distribution stations, a gas metering station and a control point. The acceptance of the gas pipeline into operation is scheduled for Dec. 31, 2019,” said the vice minister.

According to him, the construction of the gas pipeline to the city of Nur-Sultan will allow for the phased supply of 171 settlements along the gas pipeline’s gas, as well as improve the environmental condition of the city of Nur-Sultan and other settlements along the gas pipeline.

The implementation of the Saryarka gas pipeline project will have a multiplier effect on the development of small and medium-sized businesses, as well as on the development of regional infrastructure along the main gas pipeline. In addition, the use of natural gas as a fuel reduces emissions of pollutants into the atmosphere, contributes to a comfortable life for the population and contributes to an overall improvement in the environment,” the vice minister emphasized.

When will Gas Come to Nur-Sultan?

Vice Minister of Energy Murat Zhurebekov also noted that the connection of the city to the main gas pipeline will be carried out in phases. The construction of gas distribution networks is divided into three phases with construction periods until 2025.

The first is 2019-2021. The first consumers will be connected to the next heating season. These are residential areas Koktal-1, Koktal-2, Southeast, as well as TPP-1 and TPP-3. The first phase will be completed in 2020.

The terms of the second stage are 2021-2023. The gas distribution points East and Southeast will be connected. Gas will be provided in the districts of Internatsionalny, Michurino, Kotelnaya. Prigorodny, Family Village, Garden Village and the boiler room of the international airport will also be connected.

The third stage is 2023-2025. Microdistricts Ilyinka, Ondyrys, Brick Plant, and CHP-2 will be connected to gas.

The first gas consumers will be connected as early as next year, but this is not an immediate job, it is a long phased process,” said the vice minister.

Connecting Karaganda Region to Gas Pipeline

Akimat of the Karaganda region provides for the construction of branches from automated gas distribution stations to the cities of Karaganda, Temirtau and Zhezkazgan and the construction of distribution networks.

For the construction of gas distribution networks in the Karaganda region from the republican budget for this year allocated 2.4 billion tenge. Of these, 1 billion tenge for the cities of Karaganda and Zhezkazgan, 400 million tenge for the city of Temirtau.

  • 38.9 km or 90% of pipes were delivered in Karaganda, of which 28.9 km or 66.5% were welded (out of 43.4 km envisaged for 2019);
  • 29.6 km or 100% of pipes were delivered in Zhezkazgan — of which 19.7 km or 66.5% were welded;
  • 30.1 km or 100% of pipes were delivered in Temirtau — of which 16.8 km or 56% were welded.

By the end of this year, the Akimat of the Karaganda region plans to connect the first consumers of the cities of Zhezkazgan — 148 houses, Temirtau — 100 houses and Karaganda — 150 houses.

In general, according to the akimat of the Karaganda region, the completion of the construction of the first stage is scheduled for May 2020.

Gas Supply to Akmola Region

In the Akmola region, first of all, it is planned to build gas distribution networks in 20 settlements of the Arshalyn and Tselinograd districts.

Today, the akimat has received a positive conclusion of the state examination of design estimates of 8 (out of 13) projects, on which work is being carried out to determine the contracting organizations.

The deadline for obtaining a state examination opinion on the design estimates of the remaining five Projects is November 2019.

We can say that the order of Elbasy, given in the framework of the Five Social Initiatives — this is the Fifth Initiative — was executed by the Ministry of Energy. Last month, we participated in a golden welding ceremony. That is, it was the last seam welded on the main gas pipeline when supplying to the city of Nur-Sultan,” the vice minister of energy summed up.


News feed
29 May 2020, 15:56
Interdepartmental Commission decides to remove checkpoints and resume activities of several industries
28 May 2020, 15:12
Two hundred and thirty best specialists in 11 industries work to increase competitiveness of Kazakhstan
28 May 2020, 01:23
Oil production, gas supply and investment attraction — review of energy sector in Kazakhstan
27 May 2020, 11:36
Prime Minister of Kazakhstan Askar Mamin presented Dostyk Order to UAE Ambassador Mohammed Al-Jaber
26 May 2020, 19:52
Intergovernmental Commission considers issues of strengthening quarantine enforcement
26 May 2020, 11:43
Steady growth of 4% maintained in livestock industry — Ministry of Agriculture
26 May 2020, 11:04
In 2020, it is planned to sow crops on area of ​​22.5 million hectares — Ministry of Agriculture
26 May 2020, 10:51
Efforts in livestock development will be aimed at increasing self-sufficiency and exports — Askar Mamin
26 May 2020, 10:18
Kazakhstan has real potential to become one of world’s food hubs — Askar Mamin
25 May 2020, 22:33
Modernization of pharmaceutical industry and production of protective products: How Kazakhstani enterprises developed during emergency state
25 May 2020, 19:39
Interdepartmental Commission decides to resume several types of activities in regions
25 May 2020, 15:01
Government session to be held May 26 in Ukimet Uyi
24 May 2020, 11:00
Video Digest: Main events of the week, No. 62
24 May 2020, 08:38
Prime Minister Askar Mamin congratulated Kazakhstanis on Oraza Ait
23 May 2020, 22:19
Small and medium-sized enterprises, investment, and exports: What Almaty region focused on
23 May 2020, 21:38
Video Digest: Results of Prime Minister Askar Mamin’s working trip to Almaty region
23 May 2020, 17:26
Prime Minister Askar Mamin gets acquainted with state of hydraulic structures and implementation of development programs in Almaty region
22 May 2020, 16:24
Prime Minister Askar Mamin inspects restoration works in Maktaaral district of Turkistan region
21 May 2020, 12:44
Capital should be an example for all regions — Askar Mamin
20 May 2020, 18:00
Roman Sklyar discusses development of bilateral cooperation in engineering with German companies
19 May 2020, 15:22
Since beginning of 2020, 118 thousand people employed under Enbek program — Birzhan Nurymbetov
19 May 2020, 14:08
Ruslan Dalenov: Main goal of implementing Integrated Plan — to ensure employment of people
19 May 2020, 13:53
Each year, state will purchase 365 thousand tons of agricultural products
19 May 2020, 12:36
Who can purchase housing under new program 5-10-20
19 May 2020, 11:49
Integrated plan to help restore economic activity by the end of 2020 — Ruslan Dalenov
19 May 2020, 10:02
Government adopts Integrated Plan for Recovering Economic Growth
19 May 2020, 09:01
Prime Minister Askar Mamin introduces new minister of finance
19 May 2020, 08:25
Roman Sklyar inspects progress of restoration work in Turkistan region
18 May 2020, 21:03
Total supply of socially significant food products in Kazakhstan is 720 thousand tons
18 May 2020, 17:44
Interdepartmental Commission considers epidemiological situation in the country
18 May 2020, 17:03
Government session to be held May 19 in Ukimet Uyi
17 May 2020, 21:09
Fighting against unemployment and improving adjacent villages — how East Kazakhstan region developing today
17 May 2020, 09:39
Video Digest: Main events of the week, No. 61
16 May 2020, 21:33
Video Digest following Prime Minister Askar Mamin’s working trip to East Kazakhstan Region
16 May 2020, 14:36
Prime Minister Askar Mamin inspects development of Semey city and preparations for 175th anniversary of Abay
15 May 2020, 16:22
Prime Minister Askar Mamin inspects progress of spring field work and socio-economic development of East Kazakhstan region
14 May 2020, 22:52
From agriculture to tourism or how Akmola region develops its key industries
14 May 2020, 18:14
Government delegation led by Deputy Prime Minister Yeraly Tugzhanov pays working visit to Atyrau region
14 May 2020, 17:14
Labor market after emergency state: Number of vacancies and resumes increased
14 May 2020, 17:01
Prime Minister Askar Mamin holds board meeting of Baiterek Holding
14 May 2020, 13:25
Prime Minister Askar Mamin inspects progress of sowing in Akmola region
13 May 2020, 17:43
New package of measures to reopen economic sectors
13 May 2020, 16:02
Prime Minister Askar Mamin instructs regions to introduce reference standard of Smart Cities
12 May 2020, 11:45
According to results for first quarter of 2020, foreign trade turnover of Kazakhstan grew by 2.7%
12 May 2020, 11:21
In January-April 2020, oil production amounted to 31.3 million tons
12 May 2020, 10:36
In January-April 2020, pharmaceutical industry production increased by 24.2% — Ministry of Industry and Infrastructure Development
12 May 2020, 10:18
According to results of four months, state budget received 2.7 trillion tenge of revenues — Ministry of Finance
12 May 2020, 09:56
Communication services increased by 9.6% in January-April 2020 — Ministry of National Economy
12 May 2020, 09:46
Priority task for coming period will be formation of new economic structure — Askar Mamin
11 May 2020, 19:18
Government of Kazakhstan plans to gradually reduce non-oil deficit — Alikhan Smailov
© 2019 - 2020 Press service of the Prime Minister of the Republic of Kazakhstan.
Developed by SoftDeCo.